Cove Point LNG

Image description

In November 2014, Vega and WGL signed a 20-year natural gas sales agreement with a US-based subsidiary of India's national gas utility GAIL, to deliver up to 430,000 dekatherms per day of natural gas for liquefaction by Dominion at their Cove Point, Maryland facility The Cove Point facility is expected to be in service in early 2018.
< Back to Projects

Project Updates

  • 5/18/2017 - Cove Point reports construction is 89% complete.
  • 4/21/2017 - Cove Point reports construction is 84% complete.
  • 3/20/2017 - Cove Point reports construction is 79% complete.
  • 1/26/2017 - Cove Point reports construction is 69% complete.
  • 5/26/2016 - Cove Point reports construction 34% complete and reaffirms expected in-service date as December 31, 2017.